Renovation guide · Planning

How to plan a kitchen or bathroom renovation in Ottawa

Most of a kitchen or bathroom renovation is decided before anyone picks up a tool: whether anything moves, how much room each part needs, what the house is hiding, and which paperwork applies. Here is each decision, in the order it comes up.

8 min readUpdated By SS Carpentry and Renovations

White kitchen with quartz island and glass pendant lighting in Greely, Ottawa

Key takeaways

  • Decide first whether any fixture moves. Replacing cabinets with the plumbing fixtures in place needs no City building permit; moving plumbing does.
  • NKBA recommends a kitchen work aisle of at least 42 inches (48 for two cooks), and 30 inches of clear floor in front of every bathroom fixture.
  • In a house built before 1990, have a professional test for asbestos before demolition. Built before 1960, assume lead paint.
  • Electrical work is reported to the Electrical Safety Authority, separately from any building permit.
  • With a second bathroom you can live at home through the work. In a kitchen, the sink and cooktop are out during rough-in and cabinet fitting.

Does anything need to move?

The first decision shapes everything after it: do the sink, toilet, shower and tub stay where they are? The City of Ottawa exempts replacing kitchen or bathroom cabinets from a building permit, provided the plumbing fixtures remain in the same location. Plumbing alterations, additions and extensions are on its list of work that needs one, along with adding or removing walls and enlarging or moving a window. Our guide sets out the City’s full list of permit-exempt work.

Keeping the layout compared with changing it
What changesKeep the layoutChange the layout
Building permitNot needed to replace cabinets with the fixtures in placeNeeded to move plumbing, add or remove a wall, or change a window opening
City inspectionsNone, though the work must still meet the Ontario Building CodeAt the stages on the permit, such as plumbing rough-in and plumbing final
ElectricalAn ESA notification for most electrical workAn ESA notification for most electrical work
Time on site3 to 4 weeks3 to 4 weeks, plus the permit review and inspection holds

Both are routine for the kitchens and bathrooms we build. The difference is the paperwork and the calendar, which is why it is the first thing to settle. Yes. We check joist direction and plumbing clearances at the first visit so any changes meet the Ontario Building Code.

How much room does a kitchen need?

The National Kitchen & Bath Association (NKBA) publishes planning guidelines for kitchen and bathroom design. Three of its kitchen recommendations cover most layouts:

Plan of a kitchen with an island: a work aisle between the counter and the island, a walkway beyond the island, and a dashed work triangle joining the fridge, cooktop and sink.FridgeCooktopSinkABC
  • A: Work aisle: at least 42″, or 48″ for two cooks
  • B: Walkway: at least 36″
  • C: Work triangle (dashed, joining fridge, cooktop and sink): 26 ft or less in total, each leg 4 to 9 ft
A kitchen with an island, not to scale. The letters match the key and the list below it.
  • A. Work aisle: at least 42 inches. The space between facing counters, or a counter and an island, where someone cooks. NKBA recommends 48 inches when more than one person cooks.
  • B. Walkway: at least 36 inches. Any path people walk through without working in it.
  • C. Work triangle: 26 feet or less. The three distances between cooktop, sink and fridge should add up to no more than 26 feet, with no leg shorter than 4 feet or longer than 9, and no leg cutting across an island by more than 12 inches.

One more figure decides where the sink goes: NKBA recommends at least 24 inches of counter on one side of it and 18 inches on the other, so there is somewhere to put things down on both sides.

How much room does a bathroom need?

NKBA’s bathroom guidelines work the same way. It recommends 30 inches of clear floor in front of every fixture (toilet, vanity, tub and shower) before you meet a wall or another fixture, a shower at least 36 by 36 inches inside, and the centre of a sink at least 20 inches from a side wall.

If the bathroom is for someone 65 or older, or someone eligible for the disability tax credit, work that makes it safer or easier to use may qualify for the Home Accessibility Tax Credit, on up to $20,000 of eligible expenses a year.

What should you check in an older house first?

Kitchens and bathrooms are where demolition goes deepest, through tile, plaster and the layers under them. Health Canada says that before 1990, asbestos was mainly used for insulating homes, and lists floor and ceiling tiles, cement and plaster, drywall, caulking and pipe insulation among the materials that may contain it. Its advice is to have a professional test before renovating, and to have a qualified asbestos removal specialist take out anything found.

Paint is the other question. In Health Canada’s words, a home built before 1960 probably contains lead-based paint, and between 1960 and 1990 the exterior may. It says not to use sanders, heat guns or blowlamps on it. To find out, send paint chips to a lab or hire a contractor with x-ray equipment.

Which permits and notifications apply?

If the layout changes, the building permit comes first: the City says construction, including demolition, can only start once the permit is issued. The work is then inspected at the stages listed on the permit, booked at least 48 hours ahead. For a kitchen or bathroom, those can include a tested plumbing rough-in before the walls close and a tested plumbing final once the fixtures are in. Our guide to how much time a permit and its inspections add covers the review periods.

Electrical work is a separate question. Almost all of it in Ontario is reported to the Electrical Safety Authority through a notification of work, filed before the work starts, and in ESA’s words, having a building permit isn’t the same as filing an electrical notification. Plumbing on our jobs is done by a licensed plumber; electrical is done to ESA requirements, with a licensed electrician where the work calls for one.

In what order does the work happen?

Once the decisions are made, the build runs in a fixed order. On site, a kitchen or a bathroom takes us 3 to 4 weeks.

  1. Step 01

    Measure and assess

    We measure and check the layout, services and structure: joist direction, plumbing clearances, and what can move.

  2. Step 02

    Itemised quote and design

    One fixed figure, line by line, with the target build phases. A $2,000 design deposit starts the design.

  3. Step 03

    Selections

    We supply the fixtures, tile and vanities. Cabinetry is built in-house or supplied, depending on the job.

  4. Step 04

    Protection and demolition

    Dust barriers go up before anything comes out, then demolition and any framing.

  5. Step 05

    Rough-in

    New drain, supply and electrical lines. On a permitted job, the plumbing rough-in is tested and inspected before the walls are closed.

  6. Step 06

    Cabinetry and tile

    Cabinetry and tile fitted tight, starting from the same flat, stiff subfloor as the floor and tile work we do through a house.

  7. Step 07

    Fixtures and walkthrough

    Fixtures go in, the plumbing final is inspected where there’s a permit, and then the walkthrough: together we check every hinge, drawer glide, tile joint and silicone bead.

Can you live at home during the work?

“With a second bathroom, living on site is straightforward. In kitchens, sinks and cooking appliances are out of service during rough-in and cabinet fitting.”
SS Carpentry and Renovations

That shapes two things to plan before the start date:

  • For a kitchen: where you will cook and wash up during rough-in and cabinet fitting, when the sink and cooking appliances are out of service.
  • For a home’s only bathroom: which days the toilet and shower will be disconnected, so you can plan around them.

What drives the cost?

We don’t publish prices, because the honest number depends on the room and the materials. It follows a site visit as one fixed, itemised figure, the same way we price our home renovation work across Ottawa. What moves that figure most:

  • Moving fixtures. New plumbing runs, a permit and its inspections.
  • Cabinetry. Built in-house or supplied, and how much of it.
  • Tile. How much wall and floor it covers, and what the surface under it needs first.
  • Electrical changes. New circuits or moved outlets, with the ESA notification that comes with them.
  • What the walls hide. In an older house, testing, and any removal a test calls for.

Guidance only, not a design or code ruling. NKBA’s figures are design recommendations; the Ontario Building Code, the City of Ottawa and the Electrical Safety Authority set what your project must meet.

Questions

Quick answers

Not to replace the cabinets if the plumbing fixtures stay where they are: the City of Ottawa lists that as exempt from a building permit. Moving a sink, adding or removing a wall, or enlarging a window is on the City’s list of work that needs one. Exempt work must still meet the Ontario Building Code, and electrical work is reported to the Electrical Safety Authority separately.

The National Kitchen & Bath Association recommends a work aisle of at least 42 inches for one cook and 48 inches for more than one, and at least 36 inches for a walkway. These are design recommendations; the Ontario Building Code is what a renovation must meet.

If the house was built before 1990, yes. Health Canada says asbestos was mainly used for insulating homes before then, and advises hiring a professional to test before renovating or remodelling, and a qualified asbestos removal specialist if any is found.

With a second bathroom, living on site is straightforward. In kitchens, sinks and cooking appliances are out of service during rough-in and cabinet fitting.

Sources

Every figure, with its source

No figure on this page is published from memory. Each one links to the official page it was read from, on the date shown. Guide last reviewed October 5, 2026.

Sourced claims used in this guide
RefClaimPrimary sourceRead
EXEMPT-LISTThe City's exempt list includes: replacing doors or windows in the same size opening; replacing kitchen or bathroom cabinets where plumbing fixtures remain in the same location; new flooring; installing air conditioning units or heat pumps; replacing an existing hot water tank; damp proofing existing basements; installing asphalt shingles; painting and decorating; landscaping; fences not enclosing a pool; pool heaters; and a deck less than 24 inches above grade, except at the main entrance.City of Ottawa: Projects not requiring building permits (opens in a new tab)
PERMIT-REQUIRED-LISTThe City's own list of common projects that require a building permit includes: adding or removing walls (creating different room sizes or uses); enlarging or relocating a window or door; new windows where there were none before; plumbing alterations, additions or extensions (except replacing existing fixtures); and structural repairs or alterations. The City says to contact its Client Service Centre or 3-1-1 if your project is not on the list or you are unsure.City of Ottawa: Building permit projects (opens in a new tab)
EXEMPT-STILL-CODESome projects are exempt from needing a building permit, but the project must still comply with the Ontario Building Code and any applicable law, such as the Zoning By-law.City of Ottawa: Projects not requiring building permits (opens in a new tab)
NO-START-BEFORE-ISSUE“Only upon the issuance of the permit, are you legally permitted to commence construction, including any demolition of existing buildings.” Deficiencies found in review delay issuance until the requested information is received.City of Ottawa: Permit review process and timelines (opens in a new tab)
CITY-BOOK-48HThe permit holder or contractor books the building inspector at least 48 hours in advance, after each stage of construction is completed. The stages that apply are listed in the Notice to Permit Holder issued with the permit; electrical inspections are the Electrical Safety Authority’s.City of Ottawa: Inspections (opens in a new tab)
ESA-NOTIFICATIONAlmost all electrical work in Ontario must be reported to the Electrical Safety Authority by a notification of work, which should be filed before the work starts. “Having a building permit isn't the same as filing an electrical notification. You may need both.”Electrical Safety Authority: What you need to know (opens in a new tab)
NKBA-AISLERecommended: a work aisle at least 42 inches (1067 mm) wide for one cook and at least 48 inches (1219 mm) for multiple cooks; a walkway at least 36 inches (914 mm) wide.NKBA Kitchen Planning Guidelines with Access Standards (opens in a new tab)
NKBA-TRIANGLERecommended: the three travelled distances between cooking surface, sink and refrigerator total no more than 26 feet (7.9 m), with no leg under 4 feet (1.2 m) or over 9 feet (2.7 m), and no leg crossing an island or peninsula by more than 12 inches.NKBA Kitchen Planning Guidelines with Access Standards (opens in a new tab)
NKBA-LANDINGRecommended: at least 24 inches (610 mm) of landing area on one side of the sink and at least 18 inches (457 mm) on the other.NKBA Kitchen Planning Guidelines with Access Standards (opens in a new tab)
NKBA-BATHRecommended: at least 30 inches (762 mm) of clear floor space from the front of every fixture to any opposite fixture, wall or obstacle; a shower interior of at least 36 × 36 inches (914 × 914 mm); a lavatory centreline at least 20 inches (508 mm) from a side wall. NKBA’s code references are to US codes, so only its recommendations are used here.NKBA Bathroom Planning Guidelines with Access Standards (opens in a new tab)
ASBESTOS-1990Before 1990, asbestos was mainly used for insulating buildings and homes. Health Canada advises hiring a professional to test for asbestos before renovating or remodelling, and a qualified asbestos removal specialist if it is found. Materials it lists include floor and ceiling tiles, cement and plaster, drywall, caulking and sealants, and insulation around pipes.Health Canada: Asbestos and your health (opens in a new tab)
LEAD-1960A home built before 1960 probably contains lead-based paint; between 1960 and 1990, the exterior may. Health Canada says not to use sanders, heat guns or blowlamps to remove it, and to test by sending paint chips to a lab or hiring a contractor with x-ray equipment.Health Canada: Lead-based paint (opens in a new tab)
HATCThe Home Accessibility Tax Credit is a non-refundable credit on up to $20,000 per year in eligible expenses for renovations that improve safety, accessibility or functionality for a qualifying individual: 65 or older, or eligible for the disability tax credit. Claimed on line 31285.CRA: Line 31285, Home accessibility expenses (opens in a new tab)
Keep reading

Related guides

Planning a kitchen or bathroom?

Book the free estimate. We measure, check what can move, and send one fixed, itemised quote with the target build phases.

Request a QuoteCall 437-288-5105